GWR Steam Railmotor and Trailer Project

Railmotor Sheds

History

As far as is known the GWR only built two running sheds specifically for Railmotors, one at Southall on the main line out of Paddington, and one at Chalford on the Stroud Valley line. All other vehicle allocations were to established steam sheds, where they were stabled and serviced with all the other locomotives.

CHALFORD

Chalford Shed
The photograph, which is the only one known giving a clear view of Chalford shed, shows the shed and water tank from a vantage point near the station goods yard. The view is looking in the London direction, with the main line to the right of the picture
Chalford Shed
A part enlargement of a 1905 GWR drawing showing the shed location, including an amendment done in 1916 after the fire destroyed the building and a wooden coal stage was built at the end of the adjacent siding.

The Chalford shed was of wood frame construction clad with corrugated iron, with smoke troughs ventilated through chimneys in a curved roof, and was situated some 200 yards east of the station buildings adjacent to the UP (London) line. The shed was about 130‘ long, 15 ½‘ wide and 18’ to the roof ridge. Track length inside the building was 126’, and a pit was constructed outside the building for ash disposal. No coal stage was provided, coaling the railmotors being done direct from a wagon stabled on an adjacent siding, which also was used to stable a gas tank wagon to provide replenishment of the railmotor’s lighting cylinders. A tank was erected to supply water at the yard entrance.

Chalford Shed
Chalford shed site in 2006, viewed from approximately where the water tank stood. The main line to London can be seen on the right, together with the stone retaining wall detailed on the shed plan. (now covered in vegetation)

The shed and watering facilities were provided for the commencement of services between Chalford and Stonehouse on 12th October 1903 at a cost of £720, and lasted until the night of 8th January 1916, when the shed was burnt down in a mysterious fire that also destroyed Railmotor No 42, which was stabled in the shed at the time. Although the need for a new shed was acknowledged, no replacement was ever built, the railmotors being stabled and serviced in the open after that date.

SOUTHALL

The Southall shed was larger than the one at Chalford, being some 200’ long, and 19 ½’ wide. This shed was of iron frame construction rather than wood, and was clad in corrugated iron. There was a smoke trough running the length of the building venting through chimneys, and a pit ran most of the length inside the building. It was built in 1905 at the London end of Southall station, near the engine shed, adjacent to the curve of the Brentford Branch, and seems to have been “squeezed in” to a plot of land next to a margarine factory.

Southall Shed
A photo, taken from publicity leaflet produced by the margarine factory in 1912 shows the rail motor shed on the right, the Brentford Branch in mid photo, and Southall’s engine shed on the left. The main line to Paddington can just be seen on the far left. It also shows the modified roof vent arrangements fitted to the shed soon after construction.
Southall Shed

The original GWR 1905 plan shows the track running through the building for about 100’, terminating in a stop block. This (according to reports) incorporated a wooden coal stage, but a photograph from 1912 shows no evidence of this structure. There is some evidence however that the coal stage was constructed on the stop block of a siding that terminated adjacent to the external pit. (shown in brown at the left hand side of the plan) The shed was equipped with water and gas hydrants fed from the main engine shed. The early roof modification of fitting a louvred vent running the length of the roof was to improve the ventilation, the shed being notorious for the volume of smoke and dirt, so much so that it was normal practice to service the railmotors over the external pit, rather than within the building.

Southall Shed
The photograph shows the shed in later days after rail motor services had terminated and the external pit was filled in. At this time the building was used to house Auto Trailers. The pile of debris against the wall is the location of the buffer mounted coal stage.
Southall Shed
The Southall site in 2008, with the shed demolished, and the boundary wall hidden behind the trees. The margarine factory is long gone, replaced by a conglomeration of small industrial units. The Brentford branch is however still in situ, although now singled. Both this and the previous photograph were taken from the footbridge that spans the GWR main line to the east of Southall station.

The Recreation

Proposed New Shed
Side elevation of proposed shed – an extract from one of the architect’s drawings
Site for New Shed
Site Infrastructure Director Graham Drew with the tape, and architect Richard Antliff with the peg and hammer marking out the site

The GWS took the decision at a meeting of all interested parties in August 2007 to recreate one of the sheds at Didcot to house the Society’s rail motor No 93 together with trailer No 92 when restoration of the vehicles is complete. The decision to opt for a replica of the all steel constructed Southall shed was probably wise, bearing in mind the fate of the Chalford shed. The plan to construct the building is dependent on the Society obtaining ownership of the site, as obtaining the funding for construction would be virtually impossible until this is achieved. As the building will be a replica, it is not possible to obtain backing from the Heritage Lottery Fund who will only fund the restoration of original structures, so the Society must obtain funds from other sources.

PROGRESS TO DATE

A chronicle of progress to date is given below and will be progressively updated as progress in made.

Site for New Shed
The Project Team (r to l)  - Richard Antliff, Peter Jennings, Robin Stevenson, Graham Drew - 22-Aug-2008
Site for New Shed
"Grubbing out " the hedge behind the Branch Buffer Stop
22-Aug-2008
Site for New Shed
Branch extension trackwork heading for the railmotor shed site - October-2008
August 2007 Decision to build and site location agreed.
Peter Jennings appointed Project Manager
September 2007 Building design and architects drawing work commenced
The decision was taken to incorporate an educational function within the building to be housed in a separate annex. The main shed to be designed to be as faithful a reproduction of the original Southall shed as possible.
November 2007 Design and architects drawings completed
December 2007 Site cleared of vegetation.
January 2008 Planning permission granted.
April 2008 Rail access to site route agreed and pegged out.
Project officially launched in railway press
Structural engineering contract placed
June 2008 Structural engineering assessment completed
Contractors requested to quote for construction
Rail access route clearance commenced
August 2008 Initial detailed construction costings have been prepared and the first planning meeting was held on site at Didcot between the proposed building contractor and the GWS Project team, all communication up to that point being by email and phone calls.  The boundary fence between the Branch Line and the shed site was breached in preparation for track extension work to commence, and a GWR style "STOP" board has been restored by the S&T Department in preparation for erection at the current buffer stop location.
October 2008 Work has progressed on track laying over the last couple of months up to just short of the shed site. Construction costs have been evaluated, and an affordable building design has been agreed and planned that will see (subject to funding) the main core construction completed in phases within the existing timescales, with some cosmetic enhancements deferred until additional funding is available.
However it is with regret that we have to report that due to Network Rail withdrawing from an agreement made over a year ago to sell the Didcot site to the Society all work must now be put on hold until this matter is resolved. - The Society cannot raise and commit funding to a expensive building project on a site that has no security of tenure. - Additional information on this can be found on the Didcot Railway Centre website.

 

Home Page | Latest News | News Archive 2007 | News Archive 2006 | Why Railmotors ? | Railmotor 93 | Trailer 92 | Some Historical Details | Fascinating Features | The New Power Bogie | Restoring The Vehicles | Railmotor Sheds | Getting Involved
Probably the most historically-important project in railway preservation today
The Steam Railmotor Project
Great Western Society Limited
Didcot Railway Centre
Didcot
Oxon OX11 7NJ
Registered Charity No. 272616