Railmotor Sheds
History
As far as is known the GWR only built two running sheds specifically for Railmotors, one at Southall on the main line out of Paddington, and one at Chalford on the Stroud Valley line. All other vehicle allocations were to established steam sheds, where they were stabled and serviced with all the other locomotives.
CHALFORD
The Chalford shed was of wood frame construction clad with corrugated iron, with smoke troughs ventilated through chimneys in a curved roof, and was situated some 200 yards east of the station buildings adjacent to the UP (London) line. The shed was about 130‘ long, 15 ½‘ wide and 18’ to the roof ridge. Track length inside the building was 126’, and a pit was constructed outside the building for ash disposal. No coal stage was provided, coaling the railmotors being done direct from a wagon stabled on an adjacent siding, which also was used to stable a gas tank wagon to provide replenishment of the railmotor’s lighting cylinders. A tank was erected to supply water at the yard entrance.
The shed and watering facilities were provided for the commencement of services between Chalford and Stonehouse on 12th October 1903 at a cost of £720, and lasted until the night of 8th January 1916, when the shed was burnt down in a mysterious fire that also destroyed Railmotor No 42, which was stabled in the shed at the time. Although the need for a new shed was acknowledged, no replacement was ever built, the railmotors being stabled and serviced in the open after that date.
SOUTHALL
The Southall shed was larger than the one at Chalford, being some 200’ long, and 19 ½’ wide. This shed was of iron frame construction rather than wood, and was clad in corrugated iron. There was a smoke trough running the length of the building venting through chimneys, and a pit ran most of the length inside the building. It was built in 1905 at the London end of Southall station, near the engine shed, adjacent to the curve of the Brentford Branch, and seems to have been “squeezed in” to a plot of land next to a margarine factory.
The original GWR 1905 plan shows the track running through the building for about 100’, terminating in a stop block. This (according to reports) incorporated a wooden coal stage, but a photograph from 1912 shows no evidence of this structure. There is some evidence however that the coal stage was constructed on the stop block of a siding that terminated adjacent to the external pit. (shown in brown at the left hand side of the plan) The shed was equipped with water and gas hydrants fed from the main engine shed. The early roof modification of fitting a louvred vent running the length of the roof was to improve the ventilation, the shed being notorious for the volume of smoke and dirt, so much so that it was normal practice to service the railmotors over the external pit, rather than within the building.
The Recreation
The GWS took the decision at a meeting of all interested parties in August 2007 to recreate one of the sheds at Didcot to house the Society’s rail motor No 93 together with trailer No 92 when restoration of the vehicles is complete. The decision to opt for a replica of the all steel constructed Southall shed was probably wise, bearing in mind the fate of the Chalford shed. The plan to construct the building is dependent on the Society obtaining ownership of the site, as obtaining the funding for construction would be virtually impossible until this is achieved. As the building will be a replica, it is not possible to obtain backing from the Heritage Lottery Fund who will only fund the restoration of original structures, so the Society must obtain funds from other sources.
PROGRESS TO DATE
A chronicle of progress to date is given below and will be progressively updated as progress in made.
| August 2007 | Decision to build and site location agreed. Peter Jennings appointed Project Manager |
| September 2007 | Building design and architects drawing work commenced The decision was taken to incorporate an educational function within the building to be housed in a separate annex. The main shed to be designed to be as faithful a reproduction of the original Southall shed as possible. |
| November 2007 | Design and architects drawings completed |
| December 2007 | Site cleared of vegetation. |
| January 2008 | Planning permission granted. |
| April 2008 | Rail access to site route agreed and pegged out. Project officially launched in railway press Structural engineering contract placed |
| June 2008 | Structural engineering assessment completed Contractors requested to quote for construction Rail access route clearance commenced |
| August 2008 | Initial detailed construction costings have been prepared and the first planning meeting was held on site at Didcot between the proposed building contractor and the GWS Project team, all communication up to that point being by email and phone calls. The boundary fence between the Branch Line and the shed site was breached in preparation for track extension work to commence, and a GWR style "STOP" board has been restored by the S&T Department in preparation for erection at the current buffer stop location. |
| October 2008 | Work has progressed on track laying over the last couple of months up to just short of the shed site. Construction costs have been evaluated, and an affordable building design has been agreed and planned that will see (subject to funding) the main core construction completed in phases within the existing timescales, with some cosmetic enhancements deferred until additional funding is available. However it is with regret that we have to report that due to Network Rail withdrawing from an agreement made over a year ago to sell the Didcot site to the Society all work must now be put on hold until this matter is resolved. - The Society cannot raise and commit funding to a expensive building project on a site that has no security of tenure. - Additional information on this can be found on the Didcot Railway Centre website. |




